Bidder                                                  Amount

HICO                                                    No Bid

McLaren                                               No Bid

Mitsubishi Electric Power Products      Late Bid

ABB                                                      $111,096.00    

Alstom Grid                                           $79,700.00

General Pacific (Siemens Energy)        $96,262.00

 

Contract Awarded to Alstom Grid at the Board's Special Commission Meeting on Monday, August 10, 2015 @ 4:30 p.m.

 