Contractor                                             Price

Michels Power                                        No Bid

Wilson Construction                               No Bid

Titan                                                      Total (both construction and design without tax):  $1,897,699.00

DJ's Electrical                                        Total (both construction and design without tax):  $2,302,850.00

Burns & McDonnell                                Late (arrived at 11:20 a.m. via FedEx)

BIDS ARE CURRENTLY BEING EVALUATED; BID RESULTS ARE NOT OFFICIAL UNTIL A CONTRACT AWARD IS APPROVED BY THE BOARD OF COMMISSIONERS