BIDDER                                                   AMOUNT

Siemens (McKaig-Evergreen)                 $136,938.00 total (16 weeks ARO)

Alstom Grid (General Pacific)                  $145,263.00 total (20-24 weeks)

ABB (Summit Electric)                             $133,257.00 total (18 weeks ARO)

CONTRACT AWARDED TO ABB DURING COMMISSION MEETING ON MAY 7, 2018